tfs2010 - How to update current sprint team queries in TFS 2010? -


we using vs 2010 , tfs 2010 microsoft scrum template.

we use team queries current sprint sprint backlog query.

the problem when move sprint 2 "current sprint" still points sprint 1.

is there way to tell tfs in sprint 2 , have queries use variable run against instead of hard-coding sprint?

for example: if @ screen shot below notice definition of query uses variable called "@project" team project. there way have variable sprint?

alt text

tom,

what asking not available in tfs 2010. there not dates on iterations, tfs not know current iteration is.

in tfs11 (vnext) have added dates on iterations. knows in iteration are, , reflected on backlog page in web access. in preview version out not possible add filter clause queries filter on current iteration (something @currentiteration). have heard strong feedback add in product before ships. high on our wish list, need fix other things first before can ship.

you can add request on user voice. if idea gets lots of votes makes easier build case need put in. cannot promise anything.

ewald - tfs program manager


Comments

Popular posts from this blog

android - Spacing between the stars of a rating bar? -

html - Instapaper-like algorithm -

c# - How to execute a particular part of code asynchronously in a class -